7th week no progress, but ...

Moderators: Badland-F5 Pilot, LA F2 Flyer, ksatter26

Post Reply
ksatter26
Posts: 400
Joined: Mon Feb 28, 2022 9:06 am
Location: Farmersville TX

7th week no progress, but ...

Post by ksatter26 »

Polini should be back from European Vacation month. Chris expects a response from them by Monday (Labor Day).

I hope to have my real replaement CDI no later than next week.

Heard from Otatex ... half-naked, blue-red covering materials approximately $4,600. 2-3weeks delivery time. I'll probably authorize Chris to go ahead and order by the end if the week.
User avatar
Badland-F5 Pilot
Site Admin
Posts: 647
Joined: Tue Dec 14, 2021 10:32 am
Location: Dallas, TX

Re: 7th week no progress, but ...

Post by Badland-F5 Pilot »

Expensive stuff but I think Oratex in the long run will be well worth it. Would be good if Polini had a state side distribution instead of just order processing.
Post Reply